shuttering work in construction:


Shuttering or formwork is the word which is used for temporary timber, plywood, metal or other material used to provide support to Plastic concrete mix till it attains the strength or hardened state

As per IS-456 (2000), the de-shuttering period or stripping time for the RCC member is mentioned in detail, 

The de-shuttering period mentioned below only holds good, if the following three criteria or conditions are fulfilled.

Conditions:

1. The ambient temperature should not fall below 15°C.

2. The cement used for the concreting should be ordinary portland cement (OPC ).

3. Adequate curing is done.

Formwork removal time


1. Vertical member

Example - Column, Shearwall, Retaining wall, Lift wall, Beam side

vertical formwork in column


From the above drawing, the vertical formwork and props of the columns can be removed after 16 to 24 hours. To be on the safer side and to maintain the column edges, it is better to de-shutter after 24 hours of time.

vertical formwork

2. Soffit formwork to slabs - 3 days


soffit formwork

From the above drawing, the formwork which is given at the bottom part (horizontal ) of the beam or slab is called the soffit formwork.

For the slabs, we can remove the soffit formwork after 3 days, but the condition is, 

Note Props should be refixed in the same position immediately after the removal of the formwork.

3. Soffit formwork to the beams  - 7 days.


vertical formwork


From the above drawing, For the beams, we can remove the soffit formwork after  7 days


Note Props should be refixed in the same position immediately after the removal of the formwork.

4. Props Removal time for slab

a )  A slab of span which is less than or equal to 4.5m.  -  7 days.

b )  A slab having a span over 4.5m.                              -  14 days.

From the above drawing, if the clear span of the slab is less than or equal to 4.5m., the props can be removed after 7 days. If the slab has a longer span i.e. greater than 4.5m., the props should be removed after 14 days. Here, always the longer span of the slab is considered to remove the props.

5. Props left under beams & arches

a ) A beam or arch of a span which is less than or equal to 6.0m. - 14 days.

b ) A beam or arch having a span above 6m.                          -  21 days.
slab props removal

The refixed props can be removed as per the span of the RCC beams and arches. 

From the above drawing, if the clear span of the beam is less than or equal to 6.0m., the props can be removed after 14 days.





Shuttering or formwork removable time in construction


shuttering removal time for slab



Shuttering or formwork removable time in construction EXCEL Format download👇



Download Now 




QUIZ PRACTICE

RCC

RCC-1 -Click here

RCC-2- Click here

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘
SOM/MOS

SOM-1 -Click here

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘
SOIL

SOIL-1 -Click here
𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘

FLUID MECHANICS

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘

BUILDING MATERIALS

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘

SURVEY

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘

COMMENTS

Name

_GENERAL STUDIES,3,Autocad,108,BANK,1,BOOK,58,brick,1,building material,4,Building Materials,1,cement,4,cement test,1,Civil,64,CIVIL ENG,93,CIVIL FACTS,1,CIVIL JOB VACANCY,79,COMMERCIAL,2,compresive strength,1,concrete,5,current affairs,4,E-BOOK,1,EAST,3,ELECTRICAL ENG,30,ENGINEER JOB VACANCY,163,ENGINEERING,53,ESTIMATION,15,EXAM NOTES,4,EXCEL,38,GOVT,45,HIGHWAY,2,HIGHWAY ENGINEERING,2,INTERVIEW QUESTION,3,JOB,128,JOB VACANCY,199,JOBS VACANCY,12,land measurement,1,MECH ENG,121,MECH RECRUITMENT,1,MEDICAL,3,NORTH FACING,2,notes,185,paint,5,POLICE,1,Private,12,Quiz,204,RCC,4,RESIDENTIAL,9,roof slab,3,SOFTWARE,5,soil mechanics,4,SOUTH,4,SPECIAL,3,STAAD,28,steel,2,Structural analysis,2,Structural drawing,36,tiles,2,weight of steel,1,
ltr
item
CIVIL WEBSITE: deshuttering |formwork removal time |removal of formwork |shuttering removal time for slab
deshuttering |formwork removal time |removal of formwork |shuttering removal time for slab
deshuttering |formwork removal time |removal of formwork |shuttering removal time for slab
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgerLTrFhxhIXyt3Nr2J-nq9zs5p-DuzqEksaierPrF4ey9zu_34MtXIP7m51nD_9IMpKA6Av11AHfmNDm_nXT6MdS-J40E4xDKCMNKqZTDyzED0Nl-N_L1wYpBfzJLQGy50Z_WPhb5wjDg6TfC--dXgI0Qg0Jnoo1LuNzvT2s67L5fmsWtqvQDwSYB/w640-h480/Formwork%20removal%20time.jpeg
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEgerLTrFhxhIXyt3Nr2J-nq9zs5p-DuzqEksaierPrF4ey9zu_34MtXIP7m51nD_9IMpKA6Av11AHfmNDm_nXT6MdS-J40E4xDKCMNKqZTDyzED0Nl-N_L1wYpBfzJLQGy50Z_WPhb5wjDg6TfC--dXgI0Qg0Jnoo1LuNzvT2s67L5fmsWtqvQDwSYB/s72-w640-c-h480/Formwork%20removal%20time.jpeg
CIVIL WEBSITE
https://www.civilwebsite.com/2022/04/deshuttering-formwork-removal-time.html
https://www.civilwebsite.com/
https://www.civilwebsite.com/
https://www.civilwebsite.com/2022/04/deshuttering-formwork-removal-time.html
true
6778661338604217153
UTF-8
Loaded All Posts Not found any posts VIEW ALL Readmore Reply Cancel reply Delete By Home PAGES POSTS View All RECOMMENDED FOR YOU LABEL ARCHIVE SEARCH ALL POSTS Not found any post match with your request Back Home Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sun Mon Tue Wed Thu Fri Sat January February March April May June July August September October November December Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec just now 1 minute ago $$1$$ minutes ago 1 hour ago $$1$$ hours ago Yesterday $$1$$ days ago $$1$$ weeks ago more than 5 weeks ago Followers Follow THIS PREMIUM CONTENT IS LOCKED STEP 1: Share to a social network STEP 2: Click the link on your social network Copy All Code Select All Code All codes were copied to your clipboard Can not copy the codes / texts, please press [CTRL]+[C] (or CMD+C with Mac) to copy Table of Content