Rate analysis for Plain Cement Concrete 1:4:8 (M7.5):

 Rate analysis for PCC 1:4:8 (M7.5) – calculate quantity & cost, hi guys in this article we know about rate analysis for PCC grade m7.5. Rate analysis comprise of sum of material cost, labour cost, overhead expenses, contractor profit and cost of equipment or tools. And also know about cost and quantity of cement, sand aggregate & water required for 1 cubic metre of M7.5 concrete.


Rate analysis for PCC (plain cement concrete) is average an estimate for quotation and billing purpose by mason, supervisor and contractor and for tendering use.


Rate analysis for Plain Cement Concrete 1:4:8 (M7.5) / Rate analysis for PCC



 
Rate Analysis for PCC 1:4:8 :- It is a summary of all the cost involved in doing particular work or unit work like material cost, labour cost, overhead expenses, water charges & contractor profit. For rate analysis, the details about all the operation involved in carrying out the work should be available.

The quantities of materials cement sand aggregate and water are required and their cost should be known and the number of different categories of labours required and the capacity of doing work per labour and their wages per day should be known. These can be known only from the experience of particular work. Concrete structure is generally PCC for making Road,pavement, flooring, basement and etc.

READ MORE :- RATE ANALYSIS FOR PAINTING OF RESIDENTIAL HOUSE

Rate analysis for PCC 1:4:8 (M 7.5) work is summary of all the quantity and cost of material, labours overhead expenses, contractor profit charges and water charges. Rate analysis for PCC is comprise of following:-


 
● 1) quantity and cost of material ( cement sand aggregate and water quantity and their cost)

● 2) water charges ( 1 tanker)

● 3) overhead expenses (3%)
 
● 4) cost of equipment and tools (2%)

● 5) contractor profit (10%)

● 6) labour rate and cost.

Rate analysis for 1m3 PCC 1:4:8 (M7.5) work
M7.5 grade of PCC have cement, sand and aggregate ratio 1:4:8 in which one part is cement, 4 part is sand and 8 part is aggregate. For quantity and cost calculation for m7.5 grade of PCC we should follow following steps:-

HomeEstimating & CostingRate Analysis of Plain Cement Concrete (PCC) & Calculate Quantity and Cost
Rate Analysis of Plain Cement Concrete (PCC) & Calculate Quantity and Cost
Civil Work StudyMay 06, 2020

 
Rate Analysis - Plain Cement Concrete (PCC) M10 (1:3:6)
Rate Analysis of PCC
Rate Analysis of PCC

Rate analysis for Plain Cement Concrete (PCC)  requires estimation of materials for PCC, i.e. quantity of cement, sand and aggregate required for 1m3 for various proportions, i.e., PCC M10 (1:3:6), 1:2:4,  etc. So, let us first calculate quantity of cement, sand and aggregate required for 1m3 Plain Cement Concrete (PCC).

Most knowing point for rate analysis:
When you start doing rate analysis we must remember these points :
-          Item for rate analysis (Name of the Item i.e. PCC,  RCC, Brickwork etc. )
-          Specification (type of material, quality of material etc. )
-          Unit (per Sqm, Cum, Rm etc.)
-          Labour
-          Material
-          Overhead (Profit for contractor)


Labour for Plain Cement Concrete PCC work:
1)      Skilled Labour
2)      Unskilled Labour


Material for Plain Cement Concrete PCC work:
1)      Cement
2)      Sand
3)      Aggregate
 
READ MORE :- RATE ANALYSIS FOR 1m3 BRICKWORK WALL CONSTRUCTION

step 1, Dry volume :- we have wet volume of PCC work is 1m3 and we have to convert wet volume into dry volume ,we will multiply 1.54 in wet volume.

Dry volume = 1.54 × 1 = 1.54 m3.

READ MORE :- RATE ANALYSIS FOR AAC BLOCK WORK WALL CONSTRUCTION

step 2, Cement quantity:- we know that cement density is 1440 kg/m3 and 1 bag cement weight is 50 kg

Quantity of cement = 1/13 × 1.54 m3 × 1440 kg/m3 = 170 kg, no of bag cement for 1m3 PCC 1:4:8 (m7.5) = 170/50 = 3.4.

If rate of cement = INR 300 per bag, then cost of 3.4 bags cement = 3.4 ×300 = INR 1020.


 
step 3, Sand quantity :- generally sand measured in CFT and 1m3 = 35.3147

Quantity of sand = 4/13 ×1.54 × 35.3147 = 16.73 cft, so 16.73 cft sand quantity required for 1m3 PCC grade m7.5.

If market rate of sand is consider INR 40 per cft, then cost of 16.73 cft sand = 16.73 × 40 = INR 669, so cost of sand for 1m3 of PCC m7.5 grade = INR 669.

In some areas sand is measured in brass so rate of sand = INR 4000/ brass, and 1 brass sand is equal to 100 cft.

step 4, Aggregate quantity :- generally aggregate measured in CFT and 1m3 = 35.3147

Quantity of aggregate = 8/13 ×1.54 × 35.3147 = 33.47 cft, so 33.47 cft aggregate quantity required for 1m3 PCC grade m7.5

If market rate of aggregate is consider INR 50 per cft, then cost of 33.47 cft aggregate = 33.47 × 50 = INR 1674, so cost of aggregate for 1m3 of PCC grade m7.5 = INR 1674.

In some areas aggregate is measured in brass so rate of Aggregate = INR 5000/ brass, and 1 brass Aggregate is equal to 100 cft.

READ MORE :- RATE ANALYSIS FOR CEILING, EXTERNAL & INTERNAL PLASTERING

step 5, material cost :- quantity and cost of material required for 1 cubic metre of PCC m7.5 grade is sum of cost of cement sand and aggregate

Sub total cost of material = cement cost + sand cost + aggregate cost = 1020 +669 + 1674 = INR 3363.

step 6, labour rate and charges :- consider one mason and 2 helper completed 1 cubic metre of concrete work in 8 hour, per mason rate INR 600 and per Helper rate 400, but in mass concreting labour rate for 1m3 PPC work is INR 850. In some other location it will be measured in sq ft and cft also.

Labour rate is INR 12 per sq ft or INR 25 per cft for PCC work.

Labour cost for 1m3 of PCC 1:4:8 work = INR 850

Sub total cost = 3363 + 850 = INR 4213

step 7, water charges:- quantity of water required in concreting work used for preparing of mix and curing, consider 1.5% cost of water, then 1.5% of 4213 = INR 63

Sub total cost = 4213 + 63 = INR 4276

step 8, overhead expenses :- consider 2% overhead expenses,then 2% of 4213 = INR 85.

Sub total cost = 4276 + 85 = INR 4361

step 9, cost of equipment and tools :- consider cost of equipment or tools is 1.5 %,then 1.5% 



QUIZ PRACTICE

RCC

RCC-1 -Click here

RCC-2- Click here

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘
SOM/MOS

SOM-1 -Click here

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘
SOIL

SOIL-1 -Click here
𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘

FLUID MECHANICS

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘

BUILDING MATERIALS

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘

SURVEY

𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘𐩘

COMMENTS

Name

_GENERAL STUDIES,3,Autocad,108,BANK,1,BOOK,58,brick,1,building material,4,Building Materials,1,cement,4,cement test,1,Civil,64,CIVIL ENG,93,CIVIL FACTS,1,CIVIL JOB VACANCY,79,COMMERCIAL,2,compresive strength,1,concrete,5,current affairs,4,E-BOOK,1,EAST,3,ELECTRICAL ENG,30,ENGINEER JOB VACANCY,163,ENGINEERING,53,ESTIMATION,15,EXAM NOTES,4,EXCEL,38,GOVT,45,HIGHWAY,2,HIGHWAY ENGINEERING,2,INTERVIEW QUESTION,3,JOB,128,JOB VACANCY,199,JOBS VACANCY,12,land measurement,1,MECH ENG,121,MECH RECRUITMENT,1,MEDICAL,3,NORTH FACING,2,notes,185,paint,5,POLICE,1,Private,12,Quiz,204,RCC,4,RESIDENTIAL,9,roof slab,3,SOFTWARE,5,soil mechanics,4,SOUTH,4,SPECIAL,3,STAAD,28,steel,2,Structural analysis,2,Structural drawing,36,tiles,2,weight of steel,1,
ltr
item
CIVIL WEBSITE: Rate analysis for Plain Cement Concrete 1:4:8 (M7.5) / Rate analysis for PCC
Rate analysis for Plain Cement Concrete 1:4:8 (M7.5) / Rate analysis for PCC
Rate analysis for Plain Cement Concrete 1:4:8 (M7.5) / Rate analysis for PCC
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEiKmIAPr_ojRvongNBR3ftBcFp-L7hD1831__K3DNgAaIzO_NOFeHg44TwePTWjbhmBRGo_H4pZoFzTgKK7VEa-bzUxOzoLonKyfvE2YAS7pT2OL6XSbKhMJwYEV4H0lsS5rIh1cG7rc_p0iBNGogpQOvJBdmSRxj5cH5Pw4-M-qyKSIbSMDT7w2iMg/w640-h356/1.PNG
https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEiKmIAPr_ojRvongNBR3ftBcFp-L7hD1831__K3DNgAaIzO_NOFeHg44TwePTWjbhmBRGo_H4pZoFzTgKK7VEa-bzUxOzoLonKyfvE2YAS7pT2OL6XSbKhMJwYEV4H0lsS5rIh1cG7rc_p0iBNGogpQOvJBdmSRxj5cH5Pw4-M-qyKSIbSMDT7w2iMg/s72-w640-c-h356/1.PNG
CIVIL WEBSITE
https://www.civilwebsite.com/2022/06/rate-analysis-for-plain-cement-concrete.html
https://www.civilwebsite.com/
https://www.civilwebsite.com/
https://www.civilwebsite.com/2022/06/rate-analysis-for-plain-cement-concrete.html
true
6778661338604217153
UTF-8
Loaded All Posts Not found any posts VIEW ALL Readmore Reply Cancel reply Delete By Home PAGES POSTS View All RECOMMENDED FOR YOU LABEL ARCHIVE SEARCH ALL POSTS Not found any post match with your request Back Home Sunday Monday Tuesday Wednesday Thursday Friday Saturday Sun Mon Tue Wed Thu Fri Sat January February March April May June July August September October November December Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec just now 1 minute ago $$1$$ minutes ago 1 hour ago $$1$$ hours ago Yesterday $$1$$ days ago $$1$$ weeks ago more than 5 weeks ago Followers Follow THIS PREMIUM CONTENT IS LOCKED STEP 1: Share to a social network STEP 2: Click the link on your social network Copy All Code Select All Code All codes were copied to your clipboard Can not copy the codes / texts, please press [CTRL]+[C] (or CMD+C with Mac) to copy Table of Content